Confidential — Integrated Resort Operations
Problem
The programme had just over fifty requirements arriving through three intake routes — the PMO pipeline, a dated business list and ad-hoc weekly requests. There was no shared way to compare them. Sizing drifted because it used three different bases: some requirements followed a ladder, some defaulted to the smallest size, and some were stated as a single number. Without a shared model, the order was set by volume or escalation rather than by value.
Approach
Each requirement was scored on four dimensions — reach, gaming loop, spend link and dependency — and given a value score from 1 to 10. Each was sized on a T-shirt ladder with an effort range in months. The result was a portfolio, not a ranked list: roughly two-fifths in P1–P2, roughly a third in P4, the rest in P3, with most requirements sized S and only a handful sized XL or XXL.
How it was run
The model did not start as a spreadsheet. Every request that arrived — through the PMO pipeline, a dated business list or a weekly ask — was written onto a single card and put up on a board. The room sorted the cards into themes before anyone attached a number, because the argument about what a request actually is has to happen before the argument about how valuable it is.
Scoring used a written rubric rather than a show of hands: four dimensions, each defined from 0 to 3, combined into a value score from 1 to 10. Sizing then ran as a separate pass, blind to that score. Bands were applied afterwards, with a single challenge pass on the P1 boundary — the one place judgement was allowed to override the arithmetic.
Figure 1 — Five steps from a stack of requests to a portfolio
Figure 2 — Four dimensions, one value score
What we delivered
Artefacts are described at a structural level. Client content, names and commercial figures are withheld.
Impact
The model gave the programme a defensible starting portfolio. It showed that value was not a proxy for size: the two highest-value requirements were L and XL, but several S items also scored 9. It also exposed the long tail: roughly a third of requirements sat in P4, which made the cost of saying yes visible.
This page describes the workshop method, the scoring model and their output. It does not claim revenue or adoption outcomes.
Figure 3 — Value versus effort, every requirement